Home

PMP Earned Value: Variances and Indexes

Updated
2016-03-26 14:21:16
From the book
No items found.
Share
PMP Exam Prep For Dummies
PMP Exam Prep For Dummies, 2nd Edition book cover
Explore Book
Buy NowSubscribe on Perlego
PMP Exam Prep For Dummies
PMP Exam Prep For Dummies, 2nd Edition book coverExplore Book
Buy NowSubscribe on Perlego

On the PMP certification exam, you'll see five to ten questions on variances and indexes. Here's fundamental information that project managers need to determine cost and schedule variances and indexes.

  • For variance and indexes, always start with EV.

  • When looking for information on schedule, use PV.

  • When looking for information on cost, use AC.

  • For a variance, subtract.

    • SV = EV – PV

    • CV = EV – AC

    • Negative is bad; positive is good.

  • For an index, divide.

    • SPI = EV / PV

    • CPI = EV / AC

    • Less than 1.0 is bad, greater than 1.0 is good.

About This Article

This article is from the book: 

No items found.

About the book author:

No items found.