How to Resolve Resource Overloads

Step 1 of 3
Previous
Next Slideshow
Next Slideshow

Allocate your time unevenly over the duration of one or more activities.

Instead of spending the same number of hours on an activity each week, plan to spend more hours some weeks than others.

Suppose you choose to spend your hours unevenly over the duration of Activity 1 by increasing your commitment by 10 hours in the first week and reducing it by 10 hours in the third week, as depicted in the Gantt chart. The Person-Loading Graph illustrates how this uneven distribution removes your overcommitment in week 3.

  • Add a Comment
  • Print
  • Share

Recommends

Promoted Stories From Around The Web

COMMENTS »
blog comments powered by Disqus
Motivating Your Project Team with Feedback and Rewards
How to Survive Office Politics by Identifying Key Players
Ask Interview Hiring Questions Differently by Applying Critical Conversation Skills
Grasping the Role of the Project Manager
Create Powerful Action Plans using Critical Conversation Skills