How to Resolve Resource Overloads

Step 1 of 3
Next Slideshow
Next Slideshow

Allocate your time unevenly over the duration of one or more activities.

Instead of spending the same number of hours on an activity each week, plan to spend more hours some weeks than others.

Suppose you choose to spend your hours unevenly over the duration of Activity 1 by increasing your commitment by 10 hours in the first week and reducing it by 10 hours in the third week, as depicted in the Gantt chart. The Person-Loading Graph illustrates how this uneven distribution removes your overcommitment in week 3.

  • Add a Comment
  • Print
  • Share


Promoted Stories From Around The Web

blog comments powered by Disqus
How to Be an Effective Project Leader
Holding People Accountable When They Don’t Report to You
Knowing Who You Need to Involve in Planning Your Project
What to Do When You Complete a Project
How to Develop a Responsibility Assignment Matrix