How to Monitor Project-Schedule Performance
Assessing the Likelihood of a Risk in Your Project
Avoiding Project Management Pitfalls

How to Determine Nonpersonnel Resource Needs

Nonpersonnel usage charts

To estimate the amount of each resource you need, examine the nature of the task and the capacity of the resource. Ensuring that nonpersonnel resources are available when needed requires that you specify the times that you plan to use them. You can display this information in separate usage charts for each resource.

This computer usage chart depicts the amount of computer time each task requires during each week of your project. For example, the chart indicates that Task 1.2.1 requires six hours of computer time in week 1, four hours in week 2, six hours in week 3, and eight hours in each of weeks 4 and 5. You’d prepare similar charts for required copier time and use of the test lab.

  • Add a Comment
  • Print
  • Share

Recommends

Promoted Stories From Around The Web

blog comments powered by Disqus
Applying Fundamental Quality Control Concepts
Understanding and Managing Risk in Your Project
How to Introduce Quality Control to Your Organization
How to Communicate Project Risks
Resource Planning for Increasing Productivity in Your Business
Advertisement

Inside Dummies.com