A nonpersonnel resources matrix

A nonpersonnel resources matrix displays the following information for every lowest-level component (or work package) in your project Work Breakdown Structure, or WBS:

The nonpersonnel resources needed to perform the activities that comprise the work package. (For example, the figure shows that you need computers, copiers, and use of a test laboratory to complete the three listed work packages.)

The required amount of each resource. (For example, the figure suggests that you need 40 hours of computer time and 32 hours of the test laboratory to create a device.)

  • Add a Comment
  • Print
  • Share

Recommends

Promoted Stories From Around The Web

COMMENTS »
blog comments powered by Disqus
Two Ways to Estimate Indirect Costs of a Project
How to Develop a Risk-Management Strategy
Applying Fundamental Quality Control Concepts
How to Refine the Budget as a Project Progresses
How to Prepare a Risk-Management Plan