Expect to see up to 10 questions dealing with network diagrams, precedence diagramming, and scheduling issues on the PMP (Project Management Professional) Certification exam. Here are some of the details you need to know:

  • FS = Finish-to-start

  • FF = Finish-to-finish

  • SS = Start-to-start

  • SF = Start-to-finish

  • Lead = An acceleration in the relationships between activities

  • Lag = A directed delay in the relationship between activities

  • A mandatory dependency is based on the nature of the work

  • A discretionary dependency is based on a best practice or preferred way of doing something

  • An external dependency is based on a situation outside the project