PMP Earned Value: Variances and Indexes

Part of the PMP Certification All-In-One For Dummies Cheat Sheet

You'll see five to ten questions on this topic in the PMP Certification exam. Here is the fundamental information to determine cost and schedule variances and indexes.

For variance and indexes, always start with EV.

When looking for information on schedule, use PV.

When looking for information on cost, use AC.

For a variance, subtract.

SV = EV-PV
CV = EV-AC
Negative is bad; positive is good.

For an index, divide.

SPI = EV/PV
CPI = EV/AC
Less than 1.0 is bad, greater than 1.0 is good.