Allocate your time unevenly over the duration of one or more activities.

Instead of spending the same number of hours on an activity each week, plan to spend more hours some weeks than others.

Suppose you choose to spend your hours unevenly over the duration of Activity 1 by increasing your commitment by 10 hours in the first week and reducing it by 10 hours in the third week, as depicted in the Gantt chart. The Person-Loading Graph illustrates how this uneven distribution removes your overcommitment in week 3.

  • Add a Comment
  • Print
  • Share

Recommends

Promoted Stories From Around The Web

COMMENTS »
blog comments powered by Disqus
For Project Managers: How to Elicit and Sustain Commitment for Projects
Deal with Resistance using Critical Conversation Skills
How to Make Your Meetings More Effective
Minding Your Manners: Teleconference Etiquette
How to Facilitate Critical Team Conversations