How to Refine the Budget as a Project Progresses
How to Prepare a Risk-Management Plan
Identify Specific Risks Associated with Project Risk Factors

How to Determine Nonpersonnel Resource Needs

Step 1 of 3
Previous
Next Slideshow
Next Slideshow

A nonpersonnel resources matrix

A nonpersonnel resources matrix displays the following information for every lowest-level component (or work package) in your project Work Breakdown Structure, or WBS:

The nonpersonnel resources needed to perform the activities that comprise the work package. (For example, the figure shows that you need computers, copiers, and use of a test laboratory to complete the three listed work packages.)

The required amount of each resource. (For example, the figure suggests that you need 40 hours of computer time and 32 hours of the test laboratory to create a device.)

  • Add a Comment
  • Print
  • Share

Recommends

Promoted Stories From Around The Web

blog comments powered by Disqus
Flexing Your Budget: When Plans Change
How to Estimate Project Costs
How to Obtain ISO Certification to Demonstrate Quality Control Standards
How to Monitor Project Expenditures
Create a Project Budget Using the Top-Down Approach