Assessing the Likelihood of a Risk in Your Project
Implementing Quality Control Standards: How to Overcome Organizational Reluctance
How to Estimate Risk Consequences

How to Determine Nonpersonnel Resource Needs

Step 1 of 3
Next Slideshow
Next Slideshow

A nonpersonnel resources matrix

A nonpersonnel resources matrix displays the following information for every lowest-level component (or work package) in your project Work Breakdown Structure, or WBS:

The nonpersonnel resources needed to perform the activities that comprise the work package. (For example, the figure shows that you need computers, copiers, and use of a test laboratory to complete the three listed work packages.)

The required amount of each resource. (For example, the figure suggests that you need 40 hours of computer time and 32 hours of the test laboratory to create a device.)

  • Add a Comment
  • Print
  • Share


Promoted Stories From Around The Web

blog comments powered by Disqus
How to Obtain ISO Certification to Demonstrate Quality Control Standards
How to Introduce Quality Control to Your Organization
Quality Control Technique: Trimming Down with Lean Processes
Budgeting to Produce the Income Statement and Balance Sheet
How to Track and Analyze Project Expenditures